Project Location: Urea Prill Tower, Doha, Qatar

Posted on in the category Concrete Repair, Enhanced Durability for Concrete & Steel, Civil Engineering & Infrastructure, Buildings & Commercial Construction.

Advanced Cementitious Lining for Concrete Prill Tower

Protective Lining to Concrete Silo Containing Urea Prills

Background

11 metres in diameter, QAFCO’s Prill Tower is designed to allow liquid urea at 150oC to form into pellets as it drops through a counter-current of air.

Elevated operating temperatures had weakened the concrete pore system and urea at high concentrations, mixing with washdown water, had formed crystals inside the open pores and cracks, further weakening the structure.

The Solution

Inadequate reinforcement was first strengthened to prevent further cracking and, after a 1 year trial of 4 potential lining products, Cementitious Coating 851 was chosen because not only had it performed well but “its mechanical characteristics were as close to the parent concrete as possible” – a vital point for the specifying Engineers. Also important was that 851 has a degree of flexibility to cope with the varying conditions inside the Tower. With excellent abrasion, chemical and water resistance, there was no doubt that 851 would provide the sustainable lining material that would protect the concrete and give the plant trouble-free operation for many years.

Client

Qatar Fertiliser Company, Doha, Qatar

Contractor

Mouchel Group